Level Two is under construction. At the south end of the building, the framing of walls has begun for Residence 201. At the north end, plumbing sleeves, rebar, and PT cables are complete, and the concrete has been poured. With the concrete slab complete, framing crews can continue along from the south end to Residence 202, 203 and … Read More